PMP备考每日一练0002

  • 104

A project manager held a celebration to mark the successful completion of a project. At the event, the client representative notified the project manager that the final product did not meet their business needs.

What should the project manager have done to prevent this?

A.Notified stakeholders of project completion

B.Validated the project scope

C.Gathered stakeholder feedback

D.Reviewed organizational process assets updates

项目经理举行了庆祝会,庆祝项目圆满完成。在活动上,客户代表告知项目经理最终产品不满足他们的商业需求。

若要防止这个问题,项目经理事先应该做什么?

A.通知项目相关方项目完工

B.核实项目范围

C.收集项目相关方的反馈

D.审查组织过程资产更新

答案见下一页: