A risk assessment for a website project shows that implementing a specific feature is more complex than expected. This could impact project performance from both cost and schedule perspectives.
What should the project manager do next?
A.Initiate a change request to scope, add the feature to the scope exclusion, and update the risk register.
B.Log the risk in the risk register and set up a meeting with key stakeholders to discuss the risk response strategies.
C.Update the risk register, review the scope, and evaluate risk-response strategies with key stakeholders.
D.Log the risk in the risk register and continue with the project.
一个网站项目的风险评估显示,某个具体功能的实施比预期复杂。这可能同时影响项目的成本和进度绩效。
项目经理下一步应该怎么做?
A提出一项范围变更请求,将该功能添加到范围除外情况中,并更新风险登记册
B.将该风险登记进风险登记册中,并与关键相关方开会讨论风险应对策略
C.更新风险登记册,审查范围,并与关键相关方评估风险应对策略
D.将该风险登记进风险登记册,并继续项目