PMP备考每日一练0001

  • 138

A risk assessment for a website project shows that implementing a specific feature is more complex than expected. This could impact project performance from both cost and schedule perspectives.

What should the project manager do next?

A.Initiate a change request to scope, add the feature to the scope exclusion, and update the risk register.

B.Log the risk in the risk register and set up a meeting with key stakeholders to discuss the risk response strategies.

C.Update the risk register, review the scope, and evaluate risk-response strategies with key stakeholders.

D.Log the risk in the risk register and continue with the project.

一个网站项目的风险评估显示,某个具体功能的实施比预期复杂。这可能同时影响项目的成本和进度绩效。

项目经理下一步应该怎么做?

A提出一项范围变更请求,将该功能添加到范围除外情况中,并更新风险登记册

B.将该风险登记进风险登记册中,并与关键相关方开会讨论风险应对策略

C.更新风险登记册,审查范围,并与关键相关方评估风险应对策略

D.将该风险登记进风险登记册,并继续项目

答案见下一页:

  • 本文由 发表于 2022年1月6日
评论  0  访客  0

发表评论

匿名网友

:?: :razz: :sad: :evil: :!: :smile: :oops: :grin: :eek: :shock: :???: :cool: :lol: :mad: :twisted: :roll: :wink: :idea: :arrow: :neutral: :cry: :mrgreen: