项目经理、团队成员以及若干相关方共同参与一次风险研讨会。已经根据风险管理计划 生成并提供一份风险报告。若要为各个项目风险进行优先级排序,现在必须执行哪一项分析?
The project manager, team members, and Several stakeholders participated in a risk workshop.A risk report was produced and delivered according to the risk management plan. What analysis must now be performed to prioritize individual project risks?
A:定量风险分析 Quantitative risk
B:根本原因分析 Root cause
C:偏差分析 Variance
D:定性风险分析 Qualitative risk