新任命的项目经理获悉,相关方对已识别的项目问题和风险非常担心,他们对超过一个月时间里没有任何沟通表示不满。新项目经理应该怎么做?

The newly appointed project manager was informed that the stakeholders were very worried about the identified project issues and risks. They were dissatisfied with no communication for more than a month. What should the new project manager do?

A :实施现有沟通管理计划和相关方参与计划 Implement the existing communication management plan and stakeholder management plan

B :更新现有沟通管理计划和相关方参与计划,并立即向相关方提供有关问题和风险 Update the existing communication management plan and stakeholder management plan and immediately provide stakeholders with relevant issues and risks

C :与相关方开会以确定沟通所需的频率,然后立即向他们提供有关这些问题和风险 Meet with stakeholders to determine the frequency of communication needed, and then immediately provide them with these issues and risks

D : 与关键相关方开会,然后更新沟通管理计划和相关方参与计划 Meet with key stakeholders and then update the communication management plan and stakeholder management plan

正确答案:D

解析:知识点出处:PMBOK 6th 页码:P528 章节:13.3.2.5 会议:会议用于讨论和处理任何与相关方参与有关的问题或关注点。 · 问题解决; · 经验教训和回顾总结; · 项目开工; 管理相关方参与需要尽可能当面与其沟通并达成一致