一位scrum master正在领导一个敏捷项目,在该项目中,开发团队在过去的三次迭代中都未能实现冲刺的目标。在冲刺回顾中,团队决定实现几个变更来提高速度。scrum master如何验证绩效改进?
A scrum master is leading an agile project in which the development team has failed to achieve the sprint goal for the past three iterations. During the sprint retrospective, the team decides to implement several changes to improve velocity. How might the scrum master verify any performance improvement?
A :计算项目CPI Calculate the project's CPI
B :创建燃尽图 Create a burndown chart
C : 审查燃起图 Review the burnup chart
D :研究甘特图 Study the Gantt chart
正确答案:C
解析:知识点出处:敏捷实践指南 页码:P50 章节:5.2.1 回顾总结会:回顾是最重要的一个实践,原因是它能让团队学习、改进和调整其过程。 通过审查之前的绩效来进行绩效改进。B错在应该审查而非创建