你是一个项目的项目经理,你的团队与许多相关方进行过互动。你认为,为了进行客观的项目绩效评估,你需要从所有共事过的人(包括上级、同事和下属)中为项目团队成员获取反馈。团队绩效评价是在以下哪个过程中执行的?

You are the proiect manaaer of a proiect whose team has interacted w ith a number of stakeholders.You believe that in order to have an obiective proiect performance appra isal, you would like to obtain feedback for the project team members from all the people they have wo ked with, including superiors,peers and subordinates.Team performance appraisals are performed d uring which of thefollowingprocesses?

A.结束项目或阶段 CloseProjectorPhase

B.获取资源 Acquire Resources

C.管理团队 ManageTeam

D.建设团队 DevelopTeam

正确答案:

D.建设团队 Develop Team

答案解析:

团队绩效评价在建设团队过程中进行,结果随后在管理团队过程中使用。[PMBOK指南第6版,第343页]