相关方审核并批准了项目管理计划。在测试和确认阶段,其中一位关键相关方对某项需求提出顾虑,辩称需要进行一项变更,但该变更与项目范围不符。项目经理应该做什么?
The stakeholder reviews and approves the project management plan. During the testing and validation phase, one of the key stakeholders raised concerns about a certain requirement, arguing that a change was needed that did not match the project scope.What should a project manager do?
A:提出变更请求
Make a change request
B:审查变更管理问题日志
Review the change management issue log
C:从紧急情况预算中划拨资金
Allocate funds from the contingency budget
D:将该变更告知指导委员
Inform the Steering Committee of this change
正确答案:A