在发出新项目的虚拟启动会议邀请后,公司的几位资源指出提议的会议时间与进度计划发生冲突。项目经理应该做什么?
After sending out invitations for virtual launch meetings for new projects, several of the company's resources indicated that the proposed meeting schedule conflicted with the schedule. What should the project manager do?
A:修改会议议程,以便这些资源能够参会
Modify the meeting agenda so that these resources can engage
B:将该问题上报给资源经理解决
Escalate the issue to the resource manager for resolution
C:取消会议,重新安排不同的时间
Cancel the meeting and reschedule for a different time
D:如期举行启动会议
The launch meeting was held as scheduled
正确答案:C
解析:PMBOK(6)P86-4.2.2.4会议。 题干关键词“虚拟启动会议”、“与进度计划冲突”。 只需要重新调整会议时间就能解决题干所述的问题,故选C; 选项A错误,会议议程不等同于会议召开的时间; 选项B错误,项目经理可以解决的问题无需上报; 选项D错误,没有重要资源参与的启动会议就算如期召开也没有意义。