第5章题库-项目范围管理0005

  • 62

一客户给你一复杂项目的采购工作说明书,该项目为期 8 个月,未知的东西不多。客户只要你将它完成,并只希望在 8 月末你交付完成项目的时候见你。在这种情况下,下列哪种做法最好?

A customer has given you a contract statement of work for a complex, eight month project that has a few unknowns. The customer has asked you to just get it done and onlywants to see you at the end of eight months when you deliver the finished project. Under these circumstances, which of the following is the BEST thing to do?

A : 按要求完成项目,但是一直与客户时不时地确认其范围 Complete the project as requested, but validate its scope with the customer occasionally throughout.

B :在 8 个月内完成项目,期间不联系客户 Complete the project within eight months without contacting the customer during this time.

C :让管理层时不时地和客户联系 Ask management to check in with the customer occasionally.

D :完成项目,但是记录下客户不想联系 Complete the project, but document that the customer did not want contact. Procurement Management Answers

正确答案:A

解析:知识点出处:PMBOK 6th 页码:P164 章节:5.5 确认范围:由客户或发起人审查从控制质量过程输出的核实的可交付成果,确认这些可交付成果已经圆满完成并通过正式验收。本过程对可交付成果的确认和最终验收,需要依据:从项目范围管理知识领域的各规划过程获得的输出(如需求文件或范围基准),以及从其他知识领域的各执行过程获得的工作绩效数据。 确认范围是对可交付成果的实质性验收,此过程非常重要且不能省略。

  • 本文由 发表于 2022年5月22日
评论  0  访客  0

发表评论

匿名网友

:?: :razz: :sad: :evil: :!: :smile: :oops: :grin: :eek: :shock: :???: :cool: :lol: :mad: :twisted: :roll: :wink: :idea: :arrow: :neutral: :cry: :mrgreen: