由于一台设备设计规格中的某一项被忽略了而导致项目延期,而赶制此项需要更长的交货期。为避免这种情况的发生,项目经理在项目规划期间应完成下列哪一项?
A project is delayed because one item in the equipment specification has been ignored. It will require a longer lead time to catch up. To avoid this situation, the project manager should have done which of the following in project planning?
A :制定应急计划 prepare a contingency plan
B :选择更为可靠的供应商 select a more reliable supplier
C : 在识别风险过程上花费更多的努力 spend more efforts on the process of risk identification
D :确保该项不在关键路径上 ensure that the item is a not on the critical path
正确答案:C
解析:知识点出处:PMBOK 6th 页码:P411 章节:11.2.1.1 质量管理计划:质量管理计划可能列出了受不确定性或模糊性影响的一些领域,或者关键假设可能引发风险的一些领域。 为了避免,要选择在更早的一些过程。风险识别不足会导致绩效偏差。