一项目经理刚刚为一 387,000 美元的工程项目编制完风险应对计划。他下一步很可能怎么做?
A project manager has just finished the risk response plan for a U.S. $387,000 engineering project. Which of the following should he probably do NEXT?
A :确定项目总体的风险级别 Determine the overall risk rating of the project.
B :开始分析项目图纸上出现的问题 Begin to analyze the risks that show up in the project drawings.
C : 在项目的工作分解结构中增加工作包 Add work packages to the project work breakdown structure.
D :重估项目风险 Hold a project risk reassessment.