在项目审查会议期间,相关方A指出已更新一项可交付成果来反映来自相关方B的新需求。但是,相关方A未获告知并且不同意这一变更。项目经理下一步应该做什么?

During the project review session, Skateholder A indicated that it had updated a deliverable to reflect new requirements from Stakeholder B. However, Skateholder A was not informed and did not agree to the change. What should the project manager do next?

A:检查变更日志以确认相关方A的主张

Check the change log to validate the claim of stakeholder A

B:从项目中删除新需求

Remove new requirements from the project

C:要求相关方A和B之间召开会议以解决冲突

Request a meeting between stakeholders A and B to resolve the conflict

D:将新需求升级上报给项目发起人

Escalate new requirements to the project sponsor